E.ON has completed installing turbines on the Roedsand-2 windfarm.

E.ON AG, Germany’s largest utility, says it has completed installing wind turbines at its 207WM Roedsand-2 offshore windfarm in Denmark and expects it will reach full capacity in August, about two months earlier than planned.

The facility installed many of the Siemens AG turbines at a rate of about one a day and the majority now supply power to the Danish grid, Frank Mastiaux, head of E.ON’s renewable power division, told Business Week.

Roedsand-2 will produce power at full output from August 15, compared with an earlier estimate of October, E.ON said today in a note distributed by the Nord Pool power exchange.

 

More articles from this category

More news

Categories

Product Guide

News Letter

Fill in your name, company and e-mail address below for our bi-weekly newsletter.

Subscribe
Unsubscribe

Clarksons

Powered by MARIS.

Subscribe to Offshore Shipping News Online RSS

Follow Offshore Shipping News Online on Twitter

Subscribe to email updates

Sponsors

sponsorsponsorsponsor

Events

Drilling in Ice-Affected Regions
29-30 May 2013
United states, London.

Nor Shipping
04-07 June 2013
Norway, Oslo.

Onshore Operations & Maintenance Forum 2013
04-05 June 2013
Germany, Hamburg.

Caspian Oil & Gas 2013
04-07 June 2013
Azerbaijan, Baku.

OGA 2013
05-07 June 2013
Maldives, Kuala Lumpur.

More events