    GSP Bigfoot 1 successfully completes first pipelay project

    Projects and Operations // May 3, 2010

    GSP Drilling in Romania says GSP Bigfoot 1 recently completed its first project, a two week pipelay operation which saw it install a 7km long 12in diameter gas pipe to connect the Akcakoca drilling platform to a main gas pipe.

    The pipelay installation was part of the offshore construction project for the second development phase of Akcakoca gas reserve.

    GSP Licorn performed ROV support for the project and provided the pipeline integrity survey.

    GSP Bigfoot 1 was also assisted by two AHTS vessels, one of them being GSP Vega.

     