Offshore Shipping Online

A publication for the offshore shipping industry published by Clarkson Research

  • Offshore Intelligence Monthly
  • Menu

    DNV GL helps CNOOC perform first float-over in China

    Projects and Operations // July 11, 2014

    Experts from Noble Denton Marine Assurance and Advisory, part of DNV GL, have helped CNOOC perform the first float-over type platform installation in China using DP technology.

    The installation of CNOOC’s HZ25-8 DPP (Drilling Product Platform) topside was
    successfully completed in the eastern waters of the South China Sea for the Enping
    Oilfields.

    “Our cooperation with DNV GL has enabled a breakthrough for COOEC in offshore
    installation,” said Ruhua Yuan, Vice General Manager of COOEC.

    "Our experts were able to help CNOOC perform the floatover installation safely, while saving time, manpower and material resources,” said Wolfgang Wu, Regional Manager of DNV GL Oil & Gas in China.

    DNV GL’s Noble Denton Marine Assurance and Advisory experts provided technical support to CNOOC with two challenges in particular: transverse load-out and dynamic positioning of the floatover installation.

    To ensure the safety and success of the load-out and floatover operations, DNV GL applied expertise and operational experience gained from its worldwide involvement in large topside transverse load-out operations and conducted thorough testing of the ballast and DP systems on HYSY278.

    Based on the test results and taking into account the tide level in the quay and the characteristics of the ballast air compressors, DNV GL was able to optimize the loadout operational procedures and ballast sequences.

    The project first started in 2013 when DNV GL Shanghai and Singapore was invited by COOEC to cooperate on the verification of the HZ25-8 DPP topside DP floatover installation, detail design and joint installation design.

    With the load-out weight exceeding 13,000 tonnes the project was the largest transverse load-out operation in China to date.

    During the design stage, DNV GL performed DP capability analysis, time domain analysis, docking, undocking and mating analysis, in order to assess the capabilities of the DP system under different sea states and the limited weather conditions for floatover installation operation. This analysis helped the site operation.

    In addition, DNV GL engineers, DP operators and field engineers participated in the simulation test organized by COOEC in Netherlands. It simulated the docking and undocking operation under several virtual environments, enabling the team to make contingency plans in case of failure of one thruster.

     

    More articles from this category

    More news