    Relief well under way at South Timbalier 220

    News // August 7, 2013

    The Bureau of Safety and Environmental Enforcement (BSEE), US Coast Guard, and Walter Oil & Gas Corporation, through a Unified Command, continue to oversee and coordinate response efforts to secure the South Timbalier 220 natural gas Well A-3.

    Drilling began on a relief well on August 4th using the Rowan EXL-3 jack-up rig, contracted by Walter. Drilling is expected to continue for approximately 35 days.

    Many factors can affect the expected schedule including weather and the intricate work of locating the target well bore at the end of the drilling process. A relief well is drilled to intercept the target well. Once intercepted, drilling mud, followed by cement will be pumped into the well to secure it.

    All available options to safely secure the natural gas well remain under consideration. Work is moving forward on all approaches. Removal of debris material surrounding the well head began on August 2nd. This work is being conducted from the derrick barge, Performance.

    Walter is submitting procedures for well intervention work to BSEE for review and approval. Once the procedures are approved, the work would begin if direct access to the well is available.

    From visual observation, a sheen is no longer present in the area of the well. The Coast Guard continues to maintain a 500m safety zone around the site. Firefighting and other marine vessels remain onsite with personnel from Walter, Hercules, and other professional engineering contractors, and relevant federal agencies.

    BSEE's investigation into the cause of the loss of well control continues in coordination with the Coast Guard.