    GSP Bigfoot 1 completes pipeline installation for Galata platform

    Projects and Operations // October 11, 2010

    GSP Drilling reports that GSP Bigfoot 1 has completed the installation of the 10in and 6in pipeline at Galata Platform. According to its contract with Melrose Resources, the vessel installed 8.5km of 6in diameter pipeline, 14.5km of 10in diameter pipeline, as well as two secondary 1in diameter pipelines.

    The subsea pipelines connect the Kavarna-2 and Kaliakra-2 subsea wellheads to Galata Platform.

    The vessel has now returned to Constanta Sud Agigea port and is preparing or new pipeline operations.

     